APPLICATION REQUIREMENTS FOR BUILDING PERMIT

 1.) Pre-requisite Clearance (mandatory clearance before the issuance   of   Building Permit)

  • Locational Clearance issued by the Zoning Administrator (Municipal Planning and Development Office)
  • Fire Safety Clearance issued by the Municipal Fire Marshal (Bureau of Fire Protection)

2.)  Properly filled-up application forms duly signed and sealed by engineers concerned:

  • Building Permit Forms (5 copies)
  • Electrical Permit Forms (3 copies)
  • Plumbing Permit Forms (3 copies)
  • Sanitary Permit Forms (3 copies)
  • Mechanical Permit Forms (3 copies)

3.) Five (5) complete sets of Detailed Plans

4.)For construction of two-storey building:

  • Structural Design Analysis – signed and sealed by Civil Engineer at every page

5.) For construction of more than two-storey building:

  • Boring and Plate Load Test
  • Seismic Analysis

6.)Proof of Property

  • Photocopy of Transfer Certificate if Title (TCT)
  • Photocopy of tax Declaration of Property-lot (Certified True Copy) – 5 copies
  • Photocopy of Current Tax Receipt (5 copies)

7.) If property is not registered under the name of the applicant:

  • Submit 5 copies of any of the following:
  • Contract of Lease
  • Contract of Sale
  • Affidavit of Consent of the Lot Owner for the construction of building/house
  • Deed of Absolute Sale

8.) Bill of Materials and Specification (5 copies) – signed and sealed by an engineer or an architect at every page

9.) Photocopy of PTR # and PRC license of all concerned engineers and architects

REQUIREMENTS FOR OCCUPANCY PERMIT

  • Duly Accomplished Application Form for Occupancy
  • Copy of Approved Building Application Forms
  • Building Permit
  • Electrical Permit
  • Sanitary Permit
  • Mechanical Permit
  • Fire Inspection Certificate duly approved by the Municipal Fire Marshal